New Ward for North Middlesex Hospitals

3328 1 IMG 1937

New Ward for North Middlesex Hospitals

We were delighted to work recently with Premier Modular on this fast paced scheme providing additional capacity following the COVID 19 outbreak.

James Almond, Director Lead for the project for P+HS Architects said "The programme for the scheme at North Middlesex Hospital was just 12 weeks from placement of order with Premier Modular through to completion and handover on site. We provided architectural services for the delivery of this fast turn round project and are delighted with the outcome and the efficiencies the programme has brought."

The scheme provides ward accommodation of 20 beds in six 3-bed bays and one 2-bed bay. Working with Premier and the client team P+HS ensured that the scheme provided a highly functional space, with flows, adjacencies and positioning of equipment designed to support staff's day to day working. Image Courtesy of Premier Modular.